Implement Bamboo for PG & UG - complete for PG, almost complete for UG, one issue with preview remaining to be resolved
Complete PG implementation plan & System Description Document Updates PG - complete
Peer test development of PG and User Acceptance Testing of PG - complete, performance issue not fully satisfactory but will no longer delay deployment
Complete build of UG developments - incomplete, due to number of issues raised for PG that needed to be resolved
Issues
The performance issue identified has not been resolved to the full satisfaction of CAM, but has been signed off by UWP006, i.e. CAM consider the performance for some pages unacceptable but UWP have signed off the work and it is LIVE. CAM will raise this through their USG representative at the UWP board, and will deploy PG to LIVE in August hence status now returned to GREEN.
A high number of PG issues were masked by UWP006 issues, the effort in resolving these has delayed some of the UG build work, and meant that more work is now in 15/16 (32d) than was planned (23d).