July 2015

Report Date
July 2015

Achievements in Last Period

  • Implement Bamboo for PG & UG - complete for PG, almost complete for UG, one issue with preview remaining to be resolved
  • Complete PG implementation plan & System Description Document Updates PG - complete
  • Peer test development of PG and User Acceptance Testing of PG - complete, performance issue not fully satisfactory but will no longer delay deployment
  • Complete build of UG developments - incomplete, due to number of issues raised for PG that needed to be resolved

Issues

  • The performance issue identified has not been resolved to the full satisfaction of CAM, but has been signed off by UWP006, i.e. CAM consider the performance for some pages unacceptable but UWP have signed off the work and it is LIVE. CAM will raise this through their USG representative at the UWP board, and will deploy PG to LIVE in August hence status now returned to GREEN.
  • A high number of PG issues were masked by UWP006 issues, the effort in resolving these has delayed some of the UG build work, and meant that more work is now in 15/16 (32d) than was planned (23d).

Next steps

  • Complete implementation of Bamboo for UG
  • Complete User Acceptance Testing of PG
  • Deploy PG to LIVE
  • Complete build of UG developments
  • Peer test development of UG

Milestones

Target dateTitle
14-Aug-2015PG - Acceptance Sign off
18-Aug-2015UG - Deploy to TEST
19-Aug-2015PG - Deploy to LIVE
01-Sep-2015UG - Acceptance Sign off
11-Sep-2015PG - Deployment Sign off
05-Oct-2015UG - Deploy to LIVE
20-Oct-2015UG - Deployment Sign off
05-Nov-2015Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
92.0 days
Activity this month
24.0 days
Activity this year
46.0 days
Activity to date
46.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
32.0 days

Project Info

Project
CAM Enhancements to UG & PG Degree Finders
Code
STU247
Programme
Student Services (STU)
Project Manager
Sheila Fraser
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
24-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Nov-2015
Programme Priority
5
Overall Priority
Normal
Category
Discretionary