May 2015

Report Date
May 2015

Achievements in Last Period

  • Complete project planning - complete, additional funding agreed
  • Research & Development into URL Rewrite for Drupal - initial meeting to discuss the two issues identified four specific issues, and solutions to resolve all four issues identified.

Issues

  • A new feature is required to be developed by UWP006 for this to enable updates to the CAM applications, this was expected to be deployed to LIVE following the iteration starting on 11th May or 25th May, but has not been included and no dates have been given by UWP006 as to when this will be done.
  • A number of issues have been identified in UWP006 that must be resolved to to enable updates to the CAM applications to be made. These were also expected to be deployed to LIVE following the iteration starting on 11th May or 25th May, but has not been included and no dates have been given by UWP006 as to when this will be done.
  • The above two issues will mean that completion of development, and deployment to TEST and LIVE for STU247 will depend on this feature and issues being resolved and deployed via UWP006 first, and so subsequent milestones are at risk, which may impact the delivery of UWP010.

Next steps

  • Specify Bamboo configuration (PG & UG)
  • Implement Bamboo for PG
  • Complete design for URL Rewrites for Drupal - dependency on UWP006
  • Start development of PG - dependency on UWP006 for existing issue resolution:
    • Update source application output html
    • Additions to source application html output
    • Publish meta data on source application output and make available to Drupal proxy
    • Implementation plan & System Description Document updates

Milestones

16-Jul-2015PG - Deploy to TEST
28-Jul-2015PG - Acceptance Sign off
04-Aug-2015PG - Deploy to LIVE
18-Aug-2015UG - Deploy to TEST
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
92.0 days
Activity this month
3.0 days
Activity this year
6.0 days
Activity to date
6.0 days
Estimate to complete current year
62.0 days
Estimate to complete future years
24.0 days

Project Info

Project
CAM Enhancements to UG & PG Degree Finders
Code
STU247
Programme
Student Services (STU)
Project Manager
Sheila Fraser
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
24-Mar-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Nov-2015
Programme Priority
5
Overall Priority
Normal
Category
Discretionary