June 2015

Report Date
June 2015

Achievements in last period

  •  Final planned release 6 completed and deployed to Live

Issues

New Live issue has been reported and project will exceed the final estimates: issue 15.

Next Steps

  • Complete live issue support
  • Deployment SIgn Off

 

07-Jul-2015Deployment Sign off Review
07-Jul-2015Handover to Student Systems Operations
13-Jul-2015Closure
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
173.0 days
Activity this month
11.9 days
Activity this year
178.1 days
Activity to date
178.9 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
External Examiners - Support & Enhancements
Code
STU244
Programme
Student Services (STU)
Project Manager
Franck Bergeret
Project Sponsor
Tina Harrison
Current Stage
Close
Status
Closed
Start Date
15-Jul-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Programme Priority
1
Overall Priority
Higher
Category
Discretionary