June 2015
- Report Date
- June 2015
Achievements in last period
- Final planned release 6 completed and deployed to Live
Issues
New Live issue has been reported and project will exceed the final estimates: issue 15.
Next Steps
- Complete live issue support
- Deployment SIgn Off
| 07-Jul-2015 | Deployment Sign off Review |
| 07-Jul-2015 | Handover to Student Systems Operations |
| 13-Jul-2015 | Closure |
- Approved budget
- 173.0 days
- Activity this month
- 11.9 days
- Activity this year
- 178.1 days
- Activity to date
- 178.9 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days