Report for February 2014
- Report Date
- February 2014
Achievements in Last Period
- Project brief signed off and approved by WIS
Issues
- There has been a delay in getting resources assigned to this project because of competing demands from higher priority projects, but they have now been assigned, with work on the Build stage starting in mid-March
- Revised Milestones PICCL raised on 06 March
Next Period
- Build stage to commence
- Build stage to sign-off
| |||
|---|---|---|---|
28-Mar-2014 | 28-Mar-2014 |
| |
11-Apr-2014 | 11-Apr-2014 |
| |
17-Apr-2014 | 17-Apr-2014 |
| |
25-Apr-2014 | 25-Apr-2014 |
| |
02-May-2014 | 02-May-2014 |
- Approved budget
- 31.0 days
- Activity this month
- 1.2 days
- Activity this year
- 4.6 days
- Activity to date
- 4.6 days
- Estimate to complete current year
- 26.4 days
- Estimate to complete future years
- 0.0 days