July 2012 Monthly Project Report
- Report Date
- July 2012
Report by Anne Mathison for July 2012
In July Acceptance Testing was completed for the OLL HESA 2011-12 Return. Now in early August the data has been transferred from OLL Live to SITS Live. The first combined return is being produced to identify any new issues and duplicate Students in HESA and OLL.
August will involve resolving the issues that are found.
Term 3 marks will be approved by 11th August and the combined OLL HESA return will be recreated.
In August the aim is to complete the OLL part of return to limit any OLL re-runs of data creation for the Main Student HESA return.
- Approved budget
- 69.0 days
- Activity this month
- 9.0 days
- Activity this year
- 58.0 days
- Activity to date
- 58.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 15.0 days