Report for August 2012

Report Date
August 2012
  • Achievements in Last Period

Completion of DR (Disaster Recovery / Business Continuity) test

Completion of load testing of Web Applications (Web Timetables and Web Room Booking)

  • Issues

One issue with load test of Web Room Booking (WRB) under prolonged load - escalated to Scientia - on short term if this behaviour is found in live running - it can be resolved by a re-start of WRB, and does not impact the Web Timetables

  • Next Steps

Project Closure

 

10-Sep-2012Deployment Sign off Review (DSOR)
14-Sep-2012Closure (year 1 - Minimum Change)

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
620.0 days
Activity this month
27.0 days
Activity this year
27.0 days
Activity to date
631.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Shared Academic Timetabling - Year 1 - Minimum Change Implementation
Code
STU215
Programme
Student Services (STU)
Project Manager
James Thin
Project Sponsor
Nigel Brown
Current Stage
Close
Status
Closed
Start Date
05-Sep-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Dec-2012
Programme Priority
1
Overall Priority
Higher