January 2013
- Report Date
- January 2013
Achievements in Last Period
Project aims for December were to:
- Complete build and move to TEST (complete 14-Jan)
- Complete Acceptance Sign-off Review in TEST in readiness for deploy to LIVE in January (to coincide with deployment of Office365, so students have a University-provided calendar to put their meetings into) (not complete, due to prioritisation of other projects and integration of changes for SSG004 enhancement #58 into common code base for deployment).
Issues
- .
Next Steps
Project aims for February are to:
- Complete Acceptance Sign-off Review in TEST
- Deploy to LIVE
- Deployment sign-off review
| Target date | Title |
|---|---|
| 12-Feb-2013 | ASOR ESS Meetings in Calendar |
| 14-Feb-2013 | Deploy to LIVE |
| 28-Feb-2013 | DSOR ESS Meetings in Calendar |
- Approved budget
- 35.0 days
- Activity this month
- 17.0 days
- Activity this year
- 31.0 days
- Activity to date
- 31.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days