January 2013

Report Date
January 2013

Achievements in Last Period

Project aims for December were to:

  • Complete build and move to TEST (complete 14-Jan)
  • Complete Acceptance Sign-off Review in TEST in readiness for deploy to LIVE in January (to coincide with deployment of Office365, so students have a University-provided calendar to put their meetings into) (not complete, due to prioritisation of other projects and integration of changes for SSG004 enhancement #58 into common code base for deployment).

Issues

  • .

Next Steps

Project aims for February are to:

  • Complete Acceptance Sign-off Review in TEST
  • Deploy to LIVE
  • Deployment sign-off review

 

Target dateTitle
12-Feb-2013ASOR ESS Meetings in Calendar
14-Feb-2013Deploy to LIVE
28-Feb-2013DSOR ESS Meetings in Calendar

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
35.0 days
Activity this month
17.0 days
Activity this year
31.0 days
Activity to date
31.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ESS Meetings in Calendar
Code
SSG005
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
Sheila Fraser
Project Sponsor
Ian Pirie
Current Stage
Close
Status
Closed
Start Date
04-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Apr-2013
Overall Priority
Higher
Category
Discretionary