October 2012

Report Date
October 2012

Report by Sheila Fraser for September 2012

Achievements in Last Period

  • Scope of proposed enhancements drafted in project brief

Issues

  • AMBER status due to delay in agreeing project brief, not expected to have an impact on delivery in December but may do due to the subsequent impact on the timing for completing the requirements

Next Steps

  • Sign-off project brief
  • Complete requirements for proposed solution
  • Build solution and move to TEST

 

Target dateTitle
06-Nov-2012End of planning
20-Nov-2012Business Requirements
27-Nov-2012End of design and build
05-Dec-2012ASOR ESS Meetings in Calendar
10-Dec-2012Deploy to LIVE
07-Jan-2013DSOR ESS Meetings in Calendar
21-Jan-2013Project Closure

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
20.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
20.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ESS Meetings in Calendar
Code
SSG005
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
Sheila Fraser
Project Sponsor
Ian Pirie
Current Stage
Close
Status
Closed
Start Date
04-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Apr-2013
Overall Priority
Higher
Category
Discretionary