October 2012
- Report Date
- October 2012
Report by Sheila Fraser for September 2012
Achievements in Last Period
- Scope of proposed enhancements drafted in project brief
Issues
- AMBER status due to delay in agreeing project brief, not expected to have an impact on delivery in December but may do due to the subsequent impact on the timing for completing the requirements
Next Steps
- Sign-off project brief
- Complete requirements for proposed solution
- Build solution and move to TEST
| Target date | Title |
|---|---|
| 06-Nov-2012 | End of planning |
| 20-Nov-2012 | Business Requirements |
| 27-Nov-2012 | End of design and build |
| 05-Dec-2012 | ASOR ESS Meetings in Calendar |
| 10-Dec-2012 | Deploy to LIVE |
| 07-Jan-2013 | DSOR ESS Meetings in Calendar |
| 21-Jan-2013 | Project Closure |
- Approved budget
- 20.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days