Report for May 2013
- Report Date
- May 2013
Achievements in Last Period
PG Enhancements Build signed-off and UAT started.
Issues
No issues. Budget has been agreed and funding in place.
Next Steps
Completion of PG Enhancements UAT for 11/6 and delivery 13/6.
Deployment Sign-off and Closure will be done for SSG002/3 together.
Milestones
11-Jun-2013 | User Acceptance of PG prospects Enhancements (ASOR) |
13-Jun-2013 | Delivery of PG Prospectus Enhancements |
20-Jun-2013 | DSOR of PG Enhancements and UG Enhancements |
27-Jun-2013 | Closure |
- Approved budget
- 80.0 days
- Activity this month
- 13.0 days
- Activity this year
- 78.0 days
- Activity to date
- 78.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days