July 2013

Report Date
July 2013

 

Achievements in Last Period

Deployment Sign-off Closure

Issues

No issues.

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
80.0 days
Activity this month
5.0 days
Activity this year
87.0 days
Activity to date
87.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Enhancement of student marketing services
Code
SSG003
Programme
Student Services (STU)
Project Manager
Maurice Franceschi
Project Sponsor
John Cavani
Current Stage
Close
Status
Closed
Start Date
27-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2013
Programme Priority
2
Overall Priority
Normal
Category
Discretionary