June 2013
- Report Date
- June 2013
Achievements in Last Period
PG Enhancements Build deployed.
Issues
No issues.
Next Steps
Deployment Sign-off and Closure will be done for SSG002/3 together.
Milestones
09-Jul-2013 | DSOR of PG Enhancements and UG Enhancements |
16-Jul-2013 | Closure |
- Approved budget
- 80.0 days
- Activity this month
- 20.0 days
- Activity this year
- 85.0 days
- Activity to date
- 85.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days