Weekly Report - week ending 19/4/13
Enhancement of Student Marketing Services
SSG003
Project Weekly Status Report
SSG003 Project | |||||
Week ending: | Friday 19th April | ||||
Project headlines: |
| ||||
Summary status: | Overall | Schedule | Budget days taken vs. actual | Delivery of Scope | |
Green | Green | Green 58 days taken (was 40) 21 to complete (was 62)
Weekly Apps Effort - 18 days Reduction in ETC - 41 days Contingency - 21 days
|
Amber All deliverables from Project brief may not be possible due to overrun on SSG002
| ||
Project issues and risks for attention of the Board (includes all open issues and any which have changed status
Medium or high risks - the budget is an existing issue, and there is a risk to delivery of UG if UAT slips past Tuesday. https://www.projects.ed.ac.uk/project/ssg003/risks
All Issues https://www.projects.ed.ac.uk/project/ssg003/issues
|
Project activities | ||
Planned activities completed this week:
|
UG Enhancements Build PG Enhancements Requirements PG Enhancements System Design | |
Planned activities not completed this week: |
| IMPACT & ACTIONS |
| All actvities completed
| |
Activities planned for next week (week ending 3rd May) |
Resolve the Funding Issue
Task List - https://www.wiki.ed.ac.uk/display/SMSIME/SSG002%2CSSG003+Tasks+Schedule | |
Any other points of note: UG Enhancement will be delivered on 25th April, along with the applications from SSG002. There is a risk to UG if the UAT does not complete on time - may delay a day or two if it does. The project estimate to complete all build, test and delivery would total 79 days, so the total overspend on SSG002 and SSG003 combined is 20 days (+40 from SSG002, -20 from SSG003). Build was scheduled to start Monday 22nd April, but this will be pushed back to start Monday 6th May, after funding has been resolved. We would be delivering PG Enhancements by the middle of June with this start of build date.
|