Weekly Report - week ending 29/3/13
Enhancement of Student Marketing Services
SSG003
Project Weekly Status Report
SSG003 Project | |||||
Week ending: | Friday 22nd March | ||||
Project headlines: |
| ||||
Summary status: | Overall | Schedule | Budget days taken vs. actual | Delivery of Scope | |
Green | Green | Green 40 days taken (was 33) 62 to complete (was 69)
Weekly Apps Effort - 7 days Reduction in ETC - 7 days
|
Amber All deliverables from Project brief may not be possible within the budget
| ||
Project issues and risks for attention of the Board (includes all open issues and any which have changed status Estimates for UG Build after the SDS review are in line with the 20 day budget. This leaves 20 for PG for build and peer testing/ No medium or high risks - the budget is an existing issue. https://www.projects.ed.ac.uk/project/ssg003/risks
All Issues https://www.projects.ed.ac.uk/project/ssg003/issues
|
Project activities | ||
Planned activities completed this week:
|
UG Enhancements SDS Estimation and Prioritisation of requirements Confirmation of project schedule and milestones
| |
Planned activities not completed this week: |
| IMPACT & ACTIONS |
|
PG Enhancements BRD not completed. As Steven is on leave, we now expect BRD to be signed off w/c 8th APril and are aiming for the SDS to be signed off by the 12th.
| |
Activities planned for next week (week ending 12th April) |
UG Build Signed-off PG Enhancements BRD PG Enhancements SDS Task List - https://www.wiki.ed.ac.uk/display/SMSIME/SSG002%2CSSG003+Tasks+Schedule | |
Any other points of note: Jonny, the current UG developer, has been assigned to complete the UG Enhancements work. We are therefore confident on completion of all UG build by 12th April, to allow UAT to start. UAT will be more lightweight than on SSG002, due to budget limits. CAM will work from BRD. This has been accepted by project team.
Adrian, the current PG developer, has been assgined to commplete the PG Enhancements work. This will be at a 40% availability, so the elapsed tiem to deliver PG is pushed back to end of June. CAM are ok with this.
|