Weekly Report - week ending 29/3/13

Enhancement of Student Marketing Services

SSG003

 Project Weekly Status Report

 

SSG003 Project

Week ending:

Friday 22nd March

Project headlines:

  • UG Enhancements SDS Signed Off
  • UG Back End Build ready for peer testing
  • UG Front End Build started
  • First draft of PG Enhancements sent out

Summary status:

Overall

Schedule

Budget days taken vs. actual

Delivery of Scope

Green

Green

Green

40 days taken (was 33)   62 to complete (was 69)

 

 Weekly Apps Effort - 7 days Reduction in ETC - 7 days

 

 

 

 

 

 

 

 

 

Amber

All deliverables from Project brief may not be possible within the budget

 

 

 

      

 

Project issues and risks for attention of the Board (includes all open issues and any which have changed status

Estimates for UG Build after the SDS review are in line with the 20 day budget.

This leaves 20 for PG for build and peer testing/

No medium or high risks - the budget is an existing issue.

https://www.projects.ed.ac.uk/project/ssg003/risks

 

All Issues

https://www.projects.ed.ac.uk/project/ssg003/issues

 

 

 

 

 

 

 

Project activities

Planned activities completed this week:

 

 

 

UG Enhancements SDS

Estimation and Prioritisation of requirements

Confirmation of project schedule and milestones

 

Planned activities not completed this week:

 

IMPACT & ACTIONS

 

 

 

 

 

 

PG Enhancements BRD not completed.

As Steven is on leave, we now expect BRD to be signed off w/c 8th APril and are aiming for the SDS to be signed off by the 12th.

 

 

Activities planned for next week (week ending 12th April)

UG Build Signed-off

PG Enhancements BRD PG Enhancements SDS

Task List - https://www.wiki.ed.ac.uk/display/SMSIME/SSG002%2CSSG003+Tasks+Schedule

  

 

Any other points of note:  

Jonny, the current UG developer, has been assigned to complete the UG Enhancements work. We are therefore confident on completion of all UG build by 12th April, to allow UAT to start.

UAT will be more lightweight than on SSG002, due to budget limits. CAM will work from BRD. This has been accepted by project team.

 

Adrian, the current PG developer, has been assgined to commplete the PG Enhancements work. This will be at a 40% availability, so the elapsed tiem to deliver PG is pushed back to end of June.

CAM are ok with this.

 

 

 

 

 

 

 

 

 

 

 

Project Info

Project
Enhancement of student marketing services
Code
SSG003
Programme
Student Services (STU)
Project Manager
Maurice Franceschi
Project Sponsor
John Cavani
Current Stage
Close
Status
Closed
Start Date
27-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2013
Programme Priority
2
Overall Priority
Normal
Category
Discretionary