Report for April 16
- Report Date
- April 2016
Achievements
- XPR database Acceptance review was signed off on 11 April
- XPR database was deployed to Live on 14 April without any issues
- CF Upgrade Build review was signed off 18 April and is ready to move into Test
Issues
- There are issues with OPC Test and this is considered to be a certificate error. Developer is being booked to investigate and fix. This will delay the start of UAT but if fixed in time we may still make the sign off date for Acceptance of 11 May.
Next steps
- Test fixed
- Acceptance signoff for CF Upgrade by 11 May
- Deploy to Live for CF Upgrade by 23 May
Milestones
| 11-May-2016 | XPR - DSOR |
| 11-May-2016 | CF Upgrade - Acceptance Review ASOR |
| 16-May-2016 | CF Upgrade - Deploy to Live |
| 03-Jun-2016 | CF Upgrade - Deployment review DSOR |
| 10-Jun-2016 | Close |
- Approved budget
- 60.0 days
- Activity this month
- 12.0 days
- Activity this year
- 47.0 days
- Activity to date
- 47.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days