January 16
- Report Date
- January 2016
Achievements
Project brief approved and submitted to WIS week ending 5 February
Issues
The inclusion of moving the XPR database of the soon to be decommissioned MIS-FORD server was only brought to light at the meeting to review the brief. It was expected by production that the project would cover this move but there was no budget to do so as it was originally considered just a CF upgrade. Programme manager has had to source days from other budgets to cover this move.
Next steps
Completion of server set up by DevTech in conjunction with set up for Card Front Office
Build signoff
Milestones
| 18-Mar-2016 | Build Review PPBR (incs XPR) |
| 18-Apr-2016 | Acceptance Review ASOR (incs XPR) |
| 23-May-2016 | Deploy to Live CF Upgrade |
| 24-May-2016 | Deploy to Live XPR db |
| 03-Jun-2016 | Deployment review DSOR |
| 10-Jun-2016 | Close |
- Approved budget
- 50.0 days
- Activity this month
- 7.0 days
- Activity this year
- 7.0 days
- Activity to date
- 7.0 days
- Estimate to complete current year
- 42.0 days
- Estimate to complete future years
- 0.0 days