May 2016
- Report Date
- May 2016
Achievements in the last period
- The Staff updates have been deployed to live. This followed two postponements due to resource conflict and major network problems affecting service.
Issues
- Migration of CSU java application is required from infrastructure which is being decommissioned.
Next steps
- Complete migration of CSU java application.
- Decide on the next steps for the project in terms of our visitor developments.
- Approved budget
- 120.0 days
- Activity this month
- 8.0 days
- Activity this year
- 102.0 days
- Activity to date
- 102.0 days
- Estimate to complete current year
- 19.0 days
- Estimate to complete future years
- 25.0 days