May 2016

Report Date
May 2016

Achievements in the last period

  • The Staff updates have been deployed to live. This followed two postponements due to resource conflict and major network problems affecting service.

Issues

  • Migration of CSU java application is required from infrastructure which is being decommissioned.

Next steps

  • Complete migration of CSU java application.
  • Decide on the next steps for the project in terms of our visitor developments.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
8.0 days
Activity this year
102.0 days
Activity to date
102.0 days
Estimate to complete current year
19.0 days
Estimate to complete future years
25.0 days

Project Info

Project
Digital Image Submissions for Staff and Visitors
Code
SMI012
Programme
ISG - IT Service Management (SMI)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
21-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Aug-2016
Category
Discretionary