Achievements in the last period
- The Cold Fusion upgrade has been deployed to Live.
- The Staff changes have passed their UAT which is very good progress from the team.
- The Staff updates will go into Live on the 26th of May. This is a little later than planned as the team decided it would be better to wait until after the Service Owner's annual leave.
Issues
- None
Next steps
- Deploy the staff changes to live.
- Decide on the next steps for the project in terms of our visitor developments.
- Approved budget
- 145.0 days
- Activity this month
- 11.8 days
- Activity this year
- 93.5 days
- Activity to date
- 93.5 days
- Estimate to complete current year
- 26.5 days
- Estimate to complete future years
- 25.0 days