March 2016
- Report Date
- March 2016
Achievements in the last period
- Good progress has been made with SMI012. After the joining of SMI012 and SMI015 we have re-estimated and resolved the budget pushing 25 days of the 145 into next year. This will allow the correct amount of time to evaluate a plan for visitors.
- Our plan has been to take the Cold Fusion updates through the environments, then follow on with the staff updates. I am delighted to say we have both the Cold Fusion and the staff updates in Test and the UAT is commencing w/b 11th April. Good work by the teams.
Issues
- Although we have a request for Business Analysis time to study the potential visitors developments, we will still need to formulate a full plan.
Next steps
- UAT in test with a view to deploy both Cold Fusion and Staff updates by the end of the month of April.
- Update the plan and milestones for the visitors work.
- Approved budget
- 145.0 days
- Activity this month
- 12.7 days
- Activity this year
- 80.8 days
- Activity to date
- 80.8 days
- Estimate to complete current year
- 39.2 days
- Estimate to complete future years
- 25.0 days