February 2016

Report Date
February 2016

Achievements in Last Period

  • Build work is complete and awaiting the build review in the w/b 07th March.
  • Sucessfully conflicted for senior development time to peer review the build. 
  • We have agreed to add the scope of SMI015 to SMI012.  This has been planned and the plan approved by all the teams.

Issues

  • The project is Amber because of the change in Scope.
  • Although not a major issue it should be noted that the PM was on Paternity Leave for the last 10 days which was not perfect timing for the end of month activities.

Next Steps

  • Complete the Build Review.

  • Progress with the UAT.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
145.0 days
Activity this month
20.0 days
Activity this year
64.0 days
Activity to date
64.0 days
Estimate to complete current year
48.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Digital Image Submissions for Staff and Visitors
Code
SMI012
Programme
ISG - IT Service Management (SMI)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
21-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Aug-2016
Category
Discretionary