January 2016
- Report Date
- January 2016
Achievements in the last period
- We signed off the system design.
- Development has been progressing as planned.
- We have began the planning required to extend the scope of SMI012 to include the Cold Fusion Upgrade for the Card System. This is currently part of SMI015. We have an estimate for SMI015 and we can save resource spend within the SMI programme by combining the two projects.
Issues
- No issues
Next steps
- Clarify the extended scope for the Cold Fusion Upgrades.
- Sign off the Development environment.
- Approved budget
- 100.0 days
- Activity this month
- 16.0 days
- Activity this year
- 43.8 days
- Activity to date
- 43.8 days
- Estimate to complete current year
- 56.2 days
- Estimate to complete future years
- 0.0 days