November 2015

Report Date
November 2015

Achievements in the last period

  • We have finalised planning and signed off the business analysis stage of the project.
  • As agreed with our sponsor we are progressing with the Staff developments first through to deployment before looking at the Visitors.  We are dependent on COM023 and LMP006 (Cold Fusion and Library Project) respectively and our developments when we come to visitors will feed into the plans for the library.  For the staff feed we are only updating the current HR feed to card and not developing an IDM based solution. 

Issues

  • No issues.

Next steps

  • Design and a refined estimation of our development.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
9.5 days
Activity this year
16.5 days
Activity to date
16.5 days
Estimate to complete current year
83.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Digital Image Submissions for Staff and Visitors
Code
SMI012
Programme
ISG - IT Service Management (SMI)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
21-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Aug-2016
Category
Discretionary