July Report
- Report Date
- July 2016
Achievements in the last period
- Code fixes for Photo Portlet acceptance testing completed and signed off
- Agreed live deployment date confirmed as 21st July and complete
- Draft completion report produced and updated with further comments
- Collating Deployment Review sign offs
- Project Closure in progress
Issues
- Photo portlet code deployed successfully however issues encountered with notification email which had been raised and resolved via WEB009 in Test appeared in Live. This was resolved by WEB009 project team on 22nd July and retested / confirmed as working by USD
Next steps
- Deployment Review Sign off final emails to be provided and Closure approval expected at 2nd Aug meeting
The project status is GREEN
2-Aug-2016 Closure
- Approved budget
- 145.0 days
- Activity this month
- 2.0 days
- Activity this year
- 116.0 days
- Activity to date
- 116.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days