June report
- Report Date
- June 2016
Achievements in the last period
- Migration of CSU java application has been deployed via Dev, Test and Live environments completing on 28th June in advance of 1st July deadline for decommissioning
- Code fixes for Photo Portlet completed and deployed to Test ready for acceptance testing and agreeing a live deployment date
- Confirmation from Project Sponsor and Business Lead that the Visitor developments to be de-scoped from the project, this will allow the project to close earlier than planned, A date to be confirmed following code fix deployment
- Draft completion report produced
Issues
- Resolution of available Dev Tech resource to complete CSU migration on time
- Deployment sign off review agreed that code fixes needed to take place before closing project
- PICCL raised to withdraw visitor milestones from project and 16/17 forecasted resource to be removed from ASTA as project will close earlier than planned
Next steps
- Deploy code fixes to Live
- Deployment Review Sign off
- Closure approval
The project status is GREEN
TBC Close
- Approved budget
- 145.0 days
- Activity this month
- 11.0 days
- Activity this year
- 112.6 days
- Activity to date
- 112.6 days
- Estimate to complete current year
- 11.0 days
- Estimate to complete future years
- 0.0 days