June report

Report Date
June 2016

Achievements in the last period

  • Migration of CSU java application has been deployed via Dev, Test and Live environments completing on 28th June in advance of 1st July deadline for decommissioning
  • Code fixes for Photo Portlet completed and deployed to Test ready for acceptance testing and agreeing a live deployment date
  • Confirmation from Project Sponsor and Business Lead that the Visitor developments to be de-scoped from the project, this will allow the project to close earlier than planned, A date to be confirmed following code fix deployment
  • Draft completion report produced

Issues

  • Resolution of available Dev Tech resource to complete CSU migration on time
  • Deployment sign off review agreed that code fixes needed to take place before closing project
  • PICCL raised to withdraw visitor milestones from project and 16/17 forecasted resource to be removed from ASTA as project will close earlier than planned

Next steps

  • Deploy code fixes to Live
  • Deployment Review Sign off
  • Closure approval

The project status is GREEN

 

TBC         Close

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
145.0 days
Activity this month
11.0 days
Activity this year
112.6 days
Activity to date
112.6 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Digital Image Submissions for Staff and Visitors
Code
SMI012
Programme
ISG - IT Service Management (SMI)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
21-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Aug-2016
Category
Discretionary