September 2015

Report Date
September 2015

Achievements in the last period

  • The project has been kicked off and an initial scoping meeting completed.
  • After this meeting advice was taken from our sponsor on how to proceed with the staff photo submission channel.  A decision was made that we should open the image submission channel to staff in accordance with the current human resource processes.  We would not therefore be required to make changes to any upstream applications or procedures, instead concentrating on opening up the photo submission channel as an additional image option alongside the current paper based process.
  • Five potential fixes for the current card system have been identified within service.  As we currently have developer availability the team have agreed to use project resource for three of those quick fixes and will estimate the potential resource cost of the remaining two.

Issues

  • None

Next steps

  • We will complete the planning for the project and begin our analysis.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
1.5 days
Activity this year
1.5 days
Activity to date
1.5 days
Estimate to complete current year
98.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Digital Image Submissions for Staff and Visitors
Code
SMI012
Programme
ISG - IT Service Management (SMI)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
21-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Aug-2016
Category
Discretionary