March 2015
- Report Date
- March 2015
Project has started.
Planing under way.
Achievements in Last Period
- project initiated, funding secured, project website and TR code set up
Issues
- no issues of note
- no medium or high risks
Next Steps
- complete planning
Milestones
| 27-Mar-2015 | Start of Project |
| 02-Apr-2015 | End of Planning |
| 08-May-2015 | Deliver UniDesk Live for Stirling |
| 15-May-2015 | Project Closure |
- Approved budget
- 15.0 days
- Activity this month
- 1.0 day
- Activity this year
- 1.0 day
- Activity to date
- 1.0 day
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 0.0 days