- Report Date
- August 2019
Key activities/milestones since last report
Key activities since last report
- Project Proposal approved by SEP QA
- High level project plan drafted
- Kick-off meeting with Project Sponsor
- Treasury Manager post graded
Milestones achieved since last report
Key activities/milestones planned not delivered
Activities planned not delivered
Milestones planned not delivered
Upcoming activities/milestones
Upcoming activities
- Planning workshop 2
- Populate Project Briefing pack
Upcoming milestones
- Plan and approach approved by FTP Board - 8 October 2019
Key risks and issues
Risks and issues for escalation
- Issue: Change control raised with SEP QA to extend planning phase to 8 October 2019 due to other FTP priorities
New/changed risks and issues for information
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days