Status report 11 February
- Report Date
- February 2019
Achievements this period
- Initial discussion and agreement on first Work Package Scope: Final Policy Governance
- Decided not to include Forms digitisation and Recurring payments as Work Packages
- Project plan updated
- Process Requirements and relevant Process Maps prepared for Core Systems Due diligence workshops
Issues
- Full project Plan depending on detailed Core Systems supplier plans. Due diligence workshop material and sessions preparation also depend on detailed supplier plans
- Pre Core projects and work package definition depend on time availability for clarification and approval with stakeholders before they can be finalised.
Risks
Resources required for Core Systems due diligence workshops -
Core Systems require resources from both the FTP team and finance SMEs to attend an intensive schedule of due diligence workshops during Feb and Mar
(See risk register)
Next steps
- Work Package: Final Policy Governance - clarification and approval with stakeholders
- Prepare required materials for Due diligence workshops
Milestones
TBD once Work packages are discussed
May: Core systems Due diligence outputs
July: Core processes Design workshops complete
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days