Report for December 2015

Report Date
December 2015

Achievements this period

  • New code deployed to LIVE
  • Fix to resolve post-deployment  SCE008-19 tested and signed off 
  • Resources to deploy fix in January secured

Issues

  • Deployment of fix to resolve SCE008-19 failed due to suspected introduction of bug in regular patching
  • One remaining JIRA to be closed: SCE008-18

 

Next Steps

 

Milestones

15-Jan-2016Closure

 

RAG Status

The project RAG status is AMBER as the delivery is not yet complete and the closure milestone may not be achievable

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
35.0 days
Activity this month
2.0 days
Activity this year
27.0 days
Activity to date
27.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
University Seminar Site Enhancements
Code
SCE008
Programme
SCE Portfolio Projects (OTHSCE)
Project Manager
Morna Findlay
Project Sponsor
Bob Fisher
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
23-Jan-2016
Category
Discretionary