Report for December 2015
- Report Date
- December 2015
Achievements this period
- New code deployed to LIVE
- Fix to resolve post-deployment SCE008-19 tested and signed off
- Resources to deploy fix in January secured
Issues
- Deployment of fix to resolve SCE008-19 failed due to suspected introduction of bug in regular patching
- One remaining JIRA to be closed: SCE008-18
Next Steps
Milestones
15-Jan-2016 | Closure |
RAG Status
The project RAG status is AMBER as the delivery is not yet complete and the closure milestone may not be achievable
- Approved budget
- 35.0 days
- Activity this month
- 2.0 days
- Activity this year
- 27.0 days
- Activity to date
- 27.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days