Report for November 2015

Report Date
November 2015
Report by Morna Findlay for November 2015

Achievements this period

  • Build Review Approved
  • User acceptance testing completed and signed off by sponsor
  • Acceptance Review Approved
  • New Delivery milestone (10/12/15) approved

Issues

Next Steps

  • Deliver
  • Close

Milestones

 

Deliver:  10 December 2015

Close: 17 December

 

Project Status

The project status is Green

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
University Seminar Site Enhancements
Code
SCE008
Programme
SCE Portfolio Projects (OTHSCE)
Project Manager
Morna Findlay
Project Sponsor
Bob Fisher
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
23-Jan-2016
Category
Discretionary