Report for January 2014
- Report Date
- January 2015
Achievements in Last Period
- Issues with the application have been resolved
Issues
- None
Next Steps
- Project Sponsor to publicise the launch of the website
Milestones
| 03-Mar-2015 | Sign-off Review of the Deployment |
| 03-Mar-2015 | Deploy Seminar Site to LIVE |
| 17-Mar-2015 | Closure |
- Approved budget
- 112.0 days
- Activity this month
- 1.4 days
- Activity this year
- 40.1 days
- Activity to date
- 106.7 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days