July 2014
- Report Date
- July 2014
Achievements in last period
- Acceptance signed off including Load testing
- Deployed to Live
Issues
- budget overspend by more than 10%. The reasons have been summarised in project issue https://www.projects.ed.ac.uk/project/sce003/issues/4.There is also unplanned 6d carried over into 14/15.
Next Steps
- Close
| 11-Aug-2014 | Deployment sign off review DSOR |
| 25-Aug-2014 | Close |
- Approved budget
- 110.0 days
- Activity this month
- 26.0 days
- Activity this year
- 124.0 days
- Activity to date
- 124.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 6.0 days