Report for December 2019
- Report Date
- December 2019
AchievementsĀ in Last Period
-
PID approved by SEP QA on 10/12/19
-
WP2 - Requirements complete
-
WP3 - Channel Design (UX) started - wireframes complete and design validation started
-
WP4 - MyEd Component (Technical) - technical investigation started
-
WP6 - Payment API - technical investigationĀ started
Issues and Risks
- Decision to continue work on project in absence of end of planning approval (PICCL Decision 1)
- Risk that dates for delivery of core system interfaces / middleware not known or delivery of middleware is delayed (risk 1)
-
Risk that we do not find a suitable technical solution to handling payment transactions (risk 8)
Next steps
- Approve PID (scheduled for approval at SA&S Board mid Jan)
- Complete channel design (WP3)
- Complete technical investigation for MyEd Component (Technical) (WP4)
- Complete technical investigation for Payment API (WP6)
- Approved budget
- 409.0 days
- Activity this month
- 24.9 days
- Activity this year
- 112.8 days
- Activity to date
- 113.2 days
- Estimate to complete current year
- 296.0 days
- Estimate to complete future years
- 0.0 days