Update to 31 October 2019
- Report Date
- October 2019
Achievements in last period
Project
- "Evolved" model in development
-
Consultation completed To date:
-
9 Workshops
-
6 Roadshows
-
3 Town Halls
-
15 pop-ups
-
Additionally, meetings with colleges, services, student fora held and more planned
-
Risks and issues for escalation
- https://secure.projects.ed.ac.uk/unpublished/project/sas017/risks/12 - Risk of resources to carry out consultation activities in parallel with options appraisal, analysis and business case development
- https://secure.projects.ed.ac.uk/unpublished/project/sas017/risks/13 - Buy-in from key stakeholders to preferred model. This is still being developed.
Risk Log - unpublished/project/sas017/risks
Upcoming Activities
Project
- Consultation feedback analysis, and consultation report finalisation
- Options appraisal finalisation, validated against consultation feedback
- Business Case development
Milestones
| Stage | Milestone | Due Date | Complete |
|---|---|---|---|
| Initiate | Project Team Recruited | 11-Mar-2019 | Yes |
| Plan | Project Scope, Governance, Design Group membership and ToR signed-off | 12-Apr-2019 | Yes |
| Plan | Phase 1 Completion Approval - Planning Completed | 12-Apr-2019 | Yes |
| Execute | Current State Assessment (CSA) finalised | 08-Aug-2019 | Yes |
| Execute | Phase 2 Completion Approval - CSA Completed | 08-Aug-2019 | Yes |
| Execute | Options Appraisal Consultation version drafted | 08-Aug-2019 | Yes |
| Execute | Consultation Launched | 23-Aug-2019 | Yes |
| Execute | Options Appraisal finalised (OBC) | 21-Oct-2019 | No |
| Execute | Phase 3 Completion Approval | 04-Dec-2019 | No |
| Close | Project Closure | 20-Dec-2019 | No |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days