Report for May 2014
- Report Date
- May 2014
Achievements in Last Period
- Agreement and Sign-off off the Project Brief
- Authorisation of the updated budget
- Work has started on the TAD
Issues
- None
Next Steps
- Agreement on the version of PURE to be installed on the DEV environment
- Sign-off of the TAD
- Complete the build of the DEV environment and associated testing and sign-off
Milestones
| Target date | Previous date | Title |
|---|---|---|
| 16-May-2014 | 09-May-2014 | End of Planning |
| 06-Jun-2014 | 06-Jun-2014 | Build Stage Sign-off PPBR |
| 20-Jun-2014 | 20-Jun-2014 | Integration Sign-off PPIR |
| 27-Jun-2014 | 27-Jun-2014 | Acceptance Sign-off ASOR |
- Approved budget
- 66.0 days
- Activity this month
- 14.9 days
- Activity this year
- 17.9 days
- Activity to date
- 17.9 days
- Estimate to complete current year
- 48.1 days
- Estimate to complete future years
- 0.0 days