Report for May 2014

Report Date
May 2014

Achievements in Last Period

  • Agreement and Sign-off off the Project Brief
  • Authorisation of the updated budget
  • Work has started on the TAD

Issues

  • None

Next Steps

  • Agreement on the version of PURE to be installed on the DEV environment
  • Sign-off of the TAD
  • Complete the build of the DEV environment and associated testing and sign-off

Milestones

Target datePrevious dateTitle
16-May-201409-May-2014End of Planning
06-Jun-201406-Jun-2014Build Stage Sign-off PPBR
20-Jun-201420-Jun-2014Integration Sign-off PPIR
27-Jun-201427-Jun-2014Acceptance Sign-off ASOR

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
66.0 days
Activity this month
14.9 days
Activity this year
17.9 days
Activity to date
17.9 days
Estimate to complete current year
48.1 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Database Migration
Code
SAS001
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Sally Hayward
Project Sponsor
James Toon
Current Stage
Close
Status
Closed
Start Date
04-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Feb-2015
Programme Priority
2
Overall Priority
Normal
Category
Compliance