Project Report for April 2014

Report Date
April 2014

Achievements in Last Period

  • Agreement that this work will preceed ITS103
  • Completion of the brief

Issues

  • Due to the number of days available in the programme budget there may need to be some prioritisation of the non-mandatory requirements.

Next Steps

  • Business Brief and Project Plan to WIS 9th May 2014

The project is currently showing an AMBER status as the planning phase is overdue and the scope has increased from the original project proposal. This should rectify once governance has approved the changes.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
20.0 days
Activity this month
3.0 days
Activity this year
3.0 days
Activity to date
3.0 days
Estimate to complete current year
63.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PURE Database Migration
Code
SAS001
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Sally Hayward
Project Sponsor
James Toon
Current Stage
Close
Status
Closed
Start Date
04-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Feb-2015
Programme Priority
2
Overall Priority
Normal
Category
Compliance