Project Report for April 2014
- Report Date
- April 2014
Achievements in Last Period
- Agreement that this work will preceed ITS103
- Completion of the brief
Issues
- Due to the number of days available in the programme budget there may need to be some prioritisation of the non-mandatory requirements.
Next Steps
- Business Brief and Project Plan to WIS 9th May 2014
The project is currently showing an AMBER status as the planning phase is overdue and the scope has increased from the original project proposal. This should rectify once governance has approved the changes.
- Approved budget
- 20.0 days
- Activity this month
- 3.0 days
- Activity this year
- 3.0 days
- Activity to date
- 3.0 days
- Estimate to complete current year
- 63.0 days
- Estimate to complete future years
- 0.0 days