November 2016

Report Date
November 2016

Achievements this Reporting Period

  • We did this this
  • And this thing

Issues

  • We had this issue

Next Steps

  • We plan to do this next
  • And this
Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
100.0 days
Activity this month
20.0 days
Activity this year
20.0 days
Activity to date
20.0 days
Estimate to complete current year
80.0 days
Estimate to complete future years
0.0 days