November 2019

Report Date
November 2019

Achievements in Last Period:

  • Refresh in Dust, Dev and Test from live completed
  • Brief end planning completed
  • New version release notes being reviewed 

Issues:

  • n/a

Next Steps:

  • Refresh  TRN environments 
  • Upgrade Dev environment

Milestones:

 

Execute TRN refreshed 06-Dec-2019  
Build Dev upgraded 13-Dec-2019
Build Dev upgrade sign off 20-Dec-2019
Accept Test upgraded 13-Jan-2020
Accept Test upgrade signed off 17-Feb-2020
Accept TRN upgraded 28-Feb-2020
Accept Data Future environment upgraded      28-Feb-2020
Deliver Go live 06-Mar-2020
Deliver Clone DUST from Live 23-Mar-2020
Deliver 2nd refresh of Test from Live tbc 06-Apr-2020
Deliver Deployment Sign off review DSOR 13-Apr-2020
Close Closure 30-Apr-2020
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS Double Software Upgrade
Code
SAC083
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Victoria Weinsberg
Project Sponsor
Brandi Headon
Current Stage
Build
Status
In Progress
Project Classification
Run
Start Date
14-Oct-2019
Planning Date
15-Nov-2019
Delivery Date
08-Mar-2020
Close Date
30-Apr-2020
Programme Priority
6
Overall Priority
Normal
Category
Compliance

Documentation