November 2019
- Report Date
- November 2019
Achievements in Last Period:
- Refresh in Dust, Dev and Test from live completed
- Brief end planning completed
- New version release notes being reviewed
Issues:
- n/a
Next Steps:
- Refresh TRN environments
- Upgrade Dev environment
Milestones:
| Execute | TRN refreshed | 06-Dec-2019 |
| Build | Dev upgraded | 13-Dec-2019 |
| Build | Dev upgrade sign off | 20-Dec-2019 |
| Accept | Test upgraded | 13-Jan-2020 |
| Accept | Test upgrade signed off | 17-Feb-2020 |
| Accept | TRN upgraded | 28-Feb-2020 |
| Accept | Data Future environment upgraded | 28-Feb-2020 |
| Deliver | Go live | 06-Mar-2020 |
| Deliver | Clone DUST from Live | 23-Mar-2020 |
| Deliver | 2nd refresh of Test from Live tbc | 06-Apr-2020 |
| Deliver | Deployment Sign off review DSOR | 13-Apr-2020 |
| Close | Closure | 30-Apr-2020 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days