March 2019
- Report Date
- March 2019
Achievements in last period
- completed LIVE upgrade
Issues
- n/a
Next Steps​
- Deployment sign off review
- Second refresh of Test from Live
- Clone DUST
Milestones
| Milestones | Due Date |
|---|---|
| Deployment Sign Off Review (DSOR) | 25-Mar-2019 |
| Second refresh of TEST | 12-Apr-2019 |
| Clone DUST from Live | 17-Apr-2019 |
| Close | 03 May 2019 |
- Approved budget
- 200.0 days
- Activity this month
- 25.0 days
- Activity this year
- 171.0 days
- Activity to date
- 171.0 days
- Estimate to complete current year
- 25.0 days
- Estimate to complete future years
- 0.0 days