February 2019

Report Date
February 2019

Achievements in Last Period

  • completed TRN upgrade
  • completed Test regression testing

Issues

  • n/a

Next Steps​

  • LIVE upgrade week-end 8th March

Milestones

Milestones Due Date
Upgrade LIVE 10-Mar-2019
Upgrade Live - Fall Back date TBC 17-Mar-2019
Deployment Sign Off Review (DSOR) 25-Mar-2019
Second refresh of TEST 12-Apr-2019
Clone DUST from Live 17-Apr-2019
Close 03 May 2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
200.0 days
Activity this month
46.0 days
Activity this year
141.0 days
Activity to date
141.0 days
Estimate to complete current year
61.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS Double Software Upgrade
Code
SAC076
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Brandi Headon
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Oct-2018
Planning Date
23-Nov-2018
Delivery Date
11-Mar-2019
Close Date
03-May-2019
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation