December 2018
- Report Date
- December 2018
Achievements in Last Period
- completed DEV upgrade
- Signed off DEV Upgrade
Issues
- N/A
Next Steps
- complete TEST upgrade
- complete TRN refresh
Milestones
| Milestones | Due Date |
|---|---|
| Refresh TRN (Training) environment | 30-Nov-2018 |
| Upgrade TEST | 11-Jan-2019 |
| Sign off TEST upgrade - ASOR | 04-Feb-2019 |
| Upgrade TRN | 22-Feb-2019 |
| Upgrade LIVE | 10-Mar-2019 |
| Upgrade Live - Fall Back date TBC | 17-Mar-2019 |
| Deployment Sign Off Review (DSOR) | 25-Mar-2019 |
| Second refresh of TEST | 12-Apr-2019 |
| Clone DUST from Live | 17-Apr-2019 |
| Close | 03 May 2019 |