December 2018

Report Date
December 2018

Achievements in Last Period

  • completed DEV upgrade
  • Signed off DEV Upgrade

Issues

  • N/A

Next Steps​

  • complete TEST upgrade
  • complete TRN refresh

Milestones

Milestones Due Date
Refresh TRN (Training) environment 30-Nov-2018
Upgrade TEST 11-Jan-2019
Sign off TEST upgrade - ASOR 04-Feb-2019
Upgrade TRN 22-Feb-2019
Upgrade LIVE 10-Mar-2019
Upgrade Live - Fall Back date TBC 17-Mar-2019
Deployment Sign Off Review (DSOR) 25-Mar-2019
Second refresh of TEST 12-Apr-2019
Clone DUST from Live 17-Apr-2019
Close 03 May 2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS Double Software Upgrade
Code
SAC076
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Brandi Headon
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Oct-2018
Planning Date
23-Nov-2018
Delivery Date
11-Mar-2019
Close Date
03-May-2019
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation