Report for December 2018

Report Date
December 2018

Achievements in Last Period

  • JIRAs relating to the database upgrade have been completed and closed.
  • Closure report written and waiting to be distributed.

Issues

  • There are still outstanding JIRAs that production have raised after the deployment, but Dev Tech are not sure if related to the upgrade. We have a JIRA meeting on 11/01/19 to resolve this
  • We are now past the closure date resulting in an amber status. Closure date change not approved until we get clarification on the JIRAs. Due to availability of the project team, the PM was unable to set up a meeting to discuss these before the Christmas break.

 

Next Steps​

  • Close off the JIRAs
  • Closure report to be distributed and closure achieved

Milestones

Close Closure 14-Dec-2018
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Closure date in the past (14/12/2018) resulting in amber status. JIRAs raised post deployment by production, but Dev Tech unsure if caused by the upgrade. JIRAs are not causing usability issues. Closure milestone change not agreed until we get clarification on JIRAs. Meeting set up on 11/01/2019 with Production and Dev Tech to resolve and either close the JIRAs and project or extend the closure date and action the JIRAs.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
118.0 days
Activity this month
4.0 days
Activity this year
70.0 days
Activity to date
115.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS Database upgrade to Oracle 12
Code
SAC071
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Defeng Ma
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
11-May-2018
Planning Date
22-Jun-2018
Delivery Date
19-Nov-2018
Close Date
14-Dec-2018
Overall Priority
Normal
Category
Compliance