Report for October 2018
- Report Date
- October 2018
Achievements in Last Period
- UAT signed off
- Date commitment by business on go-live
- Out of hours commitment by project team members involved with the upgrade
- TRN upgrade completed
Issues
- None
Next Steps​
- TRN sign off
- Prep work for go-live
- DUST upgrade and refresh completed
Milestones
| TRN upgrade complete | 02-Nov-2018 |
| Deployment to LIVE | 19-Nov-2018 |
| Deployment Sign Off Review | 30-Nov-2018 |
| DUST upgrade complete | 30-Nov-2018 |
| Closure | 14-Dec-2018 |
- Approved budget
- 137.0 days
- Activity this month
- 8.0 days
- Activity this year
- 44.0 days
- Activity to date
- 90.0 days
- Estimate to complete current year
- 45.0 days
- Estimate to complete future years
- 0.0 days