May 2019
- Report Date
- May 2019
Achievements in the Last Period
- New developer recruited (Dan) is making a significant contribution (10 weeks in place).
- Two new releases deployed in May- 4 releases achieved so far
- Projects resources are also being used to support the service: 3 live issues have been fixed in May
- Communication: the sharepoint site shared with users has its usage (105 views for the last release news) LINK
- User group set up with schools, 1st meeting held, 17 participants to ensure the changes meet their needs LINK
Issues
- The recruited BA has left after 1 month. This is difficult for new member of staff to join a challenging existing project.
- Live APT issue has been addressed as a priority , meaning less work on the backlog .The completion of the backlog is slowed down as the team also supports the Live Service/BAU, especially during this peak Exam Boards period
- Backlog of SOP procedures to write and handover to Operations: around 50 outstanding. Task is for BA to complete those support tasks in addition to current analysis . This will impact the BA time to focus on project time. New releases will include the SOP when required
Risks
Risk register is in https://secure.projects.ed.ac.uk/unpublished/project/sac063/risks?field_project_risk_active_status_value=Open
- No amber/red risk
Next Steps
- Progressing with next releases as per prioritised bugs list;https://uoe.sharepoint.com/sites/AssessmentandProgressionTools/SitePages/Development-Work.aspx?web=1
- Continue documenting SOP procedures (lower priority)
Releases in May

Additional support issues addressed
|
Live issue |
Benefit |
Live date |
|
Set up assessment screen not accessible |
Removed risk to delay Exam Boards |
29 May |
|
Export marks sort doesn't work when a course has assessment groups |
Clearer information for all staff. Reduced support time |
8 May
|
|
Undo resit in the 'i' screen will undo all course results & data fix |
Correct resit information displayed during Exam Boards. |
1 May |
| Attachment | Size |
|---|---|
| 24 KB |
- Approved budget
- 522.0 days
- Activity this month
- 31.0 days
- Activity this year
- 215.0 days
- Activity to date
- 435.0 days
- Estimate to complete current year
- 88.0 days
- Estimate to complete future years
- 0.0 days