March 2017

Report Date
March 2017

Achievements in Last Period

  • Project Closure achieved

Open issues

  • no issues

Next Steps

Milestones

24-Mar-2017

Acceptance Signoff and Handover

31-Mar-2017

Closure

 

Risks

no escalated risks

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
93.0 days
Activity this month
0.5 days
Activity this year
88.5 days
Activity to date
88.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Graduations
Code
SAC060
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Shirley McCulloch
Project Sponsor
Robert Lawrie
Current Stage
Close
Status
Closed
Start Date
01-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal
Category
Discretionary