Report for May 2017
- Report Date
- May 2017
Achievements in this reporting period:
- I1- Meeting arranged with MSL technical staff to discuss development strategy.
- I5 - Discussions are on-going on whether the code will be CAHSS or AHSS. Expecting deployment to be with Org Hierarchy changes on 1 August 17.
- I6 - Annual review - MSc by research programmes excluded from annual review creation
- I7 - Deployment to be co-ordinated with MyEd upgrade. This work is being taken forward by Student Systems Operations.
- I8 - AppsMan have confirmed that the php upgrades will not be within 16/17, so this has been withdrawn and will be included in 17/18.
- I10 - initial investigation complete
- I11 - preliminary discussions held
Resolved issues:
Open issues:
Next Steps:
- I1 - Meetings with EUSU and MSL staff to agree development plans for the run up to the start of term.
- I5 - Get confirmation that will be included with Org Hierarchy changes and whether this will be taken forward by Student Systems Operations.
- I6 - Annual Review - New process required to address excluded collaborative programmes which is reviewing the process for all programmes identified for an annual review
- I10 - Team to review & agree standards. Any changes required will then be scheduled.
- I11 - Resource to be allocated.
- Approved budget
- 120.0 days
- Activity this month
- 5.0 days
- Activity this year
- 42.0 days
- Activity to date
- 42.0 days
- Estimate to complete current year
- 80.0 days
- Estimate to complete future years
- 0.0 days