Report for August 2016
- Report Date
- August 2016
Achievements in this reporting period:
- SAC043 - I24- Outstanding External Examiner fix problem identified after deployment signed off in TEST. Will go live with next standard config upload.
- I1 - EUSU Technical developments are complete, policy issue is still progressing.
- I2 - SIMD. SRA confirmed that the 2012 data would be used for another year, so development could be delayed.
- I3 - Mobility. Chased ITI for the firewall, but no progress
- Various discussions which may lead to Improvements on changes to support:
- OLL becoming the Centre for Open Learning and having permissions of a School
- HSS becoming CAHSS with changes of ownership of courses and programmes and other related problems.
Resolved issues:
Open issues:
- SAC043 - I26 - Survey Channel. Dev MyEd is not working for the build to progress. This is being addressed with vendor (jira WEB009-91)
Next Steps:
- Complete Brief
- Prioritise identified improvements so have a plan of work.
- SAC043 - I24- Outstanding External Examiners rework to deploy.
- I1 - resolve policy issue and depending on outcome, complete required tasks for deployment.
- I2 - This improvement will be revisited in early 2017, so there will be no updates until then.
- I3 - Once firewall opened, will work with SOP for their changes.
- Work on getting to a position on whether the OLL &/or HSS changes need to be made.
| 16-Sep-2016 | Brief Sign Off |
- Approved budget
- 120.0 days
- Activity this month
- 6.0 days
- Activity this year
- 6.0 days
- Activity to date
- 6.0 days
- Estimate to complete current year
- 118.0 days
- Estimate to complete future years
- 0.0 days