Report for January 2017
- Report Date
- January 2017
Achievements in this reporting period:
- new budget and milestones approved
- new scope approved
- four temporary servers delivered
- process to switch named user to named temporary server delivered
- improvements to analytics delivered
- operations confirmed performance acceptable
- deployment sign off review held
Resolved issues:
- n/a
Open issues:
- n/a
Next Steps:
- Project to close
Project Milestones
Closure: Feb 17 2017
Next Steps:
The project RAG status is GREEN.
- Approved budget
- 87.0 days
- Activity this month
- 8.0 days
- Activity this year
- 64.0 days
- Activity to date
- 88.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days