Report for December 2016
- Report Date
- December 2016
Achievements in this reporting period:
- delivery of analytics expected to assist in diagnosis of performance problems
- analytical data now being collected and reviewed
- consultations held with users of admissions processes in all three colleges
- options appraisal held in order to plan for increased load on admissions after 16th January
- agreement reached to order 4 additional servers to be ready in January
Resolved issues:
- n/a
Open issues:
- new budget to be approved
- project closure delayed
Next Steps:
- New servers to be prepared in anticipation of increased load in January
- Checkpoint meeting to be heldf w/c 16 January to review performance reports
- Agreement to be reached on new project scope
- Project to close
The project RAG status is RED as the budget for this year has been exceeded and the scope is not approved.
- Approved budget
- 82.0 days
- Activity this month
- 10.0 days
- Activity this year
- 55.0 days
- Activity to date
- 79.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 0.0 days