October 2016

Report Date
October 2016
Report Date
October 2016

Achievements in Last Period

  • Website is now available in the LIVE Environment via links from SRA website

Resolved Issues

None

Open issues

  • The schools filter is excluding schools which have their status updated by a UCAS import to be anything excep "LIVE".  This is being resolved.

 

Next Steps

  • Signoff Deployment 

 

07-Oct-2016 End of Testing    
12-Oct-2016 Acceptance Sign off    
14-Oct-2016 Deployment sign off    
18-Oct-2016 Deployment go live    
11-Nov-2016 Close Project
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
RED (no issues) due to approved increase in project budget.
Change Status
Activity
Approved budget
0.0 days
Activity this month
8.0 days
Activity this year
80.0 days
Activity to date
80.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Widening Participation Contextual Admissions Checker
Code
SAC054
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Shirley McCulloch
Project Sponsor
Ian Sutherland
Current Stage
Close
Status
Closed
Start Date
24-Jun-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
14-Dec-2016
Overall Priority
Normal
Category
Discretionary