Report for June 2016
- Report Date
- June 2016
Achievements in Last Period
- Initial round of usability testing conducted
- First draft of changes to EUCLID communication changes completed and passed to Schools to review
- Workshop held with user group to determine requirements for integrating School/proramme specific data into the workflow
- Estimates for taking protptype to live service being gathered to produce project proposal
- Accessibility review of prototype completed
Resolved Issues
n/a
Open Issues
n/a
Next Steps
- Carry out end-to-end usability testing with students
- Document output from usability testing and accessibility review and add to proposal to move to live service
- Implement changes to EUCLID communications
- Complete proposals for next phase of project, including resource and cost requirements
| 15-Jul-2016 | Plan for Delivery to Live Complete |
| 22-Jul-2016 | Project Sign-Off |
| 29-Jul-2016 | Project Closure |
- Approved budget
- 5.0 days
- Activity this month
- 0.0 days
- Activity this year
- 2.0 days
- Activity to date
- 2.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days